Project Close-Out

See the requirements for construction in the Presidio.

The close-out process is the final project milestone. Project close-out formally establishes the acceptance of the improvements by and the transfer of maintenance to the Trust.

3.1 Occupancy

3.1.1 Temporary Certificate of Occupancy (TCO)

A TCO may be issued upon request when a project is substantially complete. The TCO allows for office set-up, marketing efforts and other similar activities. No business activity may be conducted in space covered by a TCO. A TCO will not be issued without inspection by and approval from the FPO, the Director of Public Safety and Municipal Services and the Permitting Manager. 

3.1.2 Certificate of Occupancy (“CO”)

A building or space cannot be occupied or used and no change in occupancy can commence until the Permitting Manager has issued a CO. The CO pertains to building and life-safety codes and signifies satisfactory completion of the building permit requirements, as confirmed by the FPO, the Director of Public Safety and Municipal Services, the Permitting Manager and relevant inspectors, including special inspectors. 

3.2 Close-Out Submittals – Required for All Projects

Unless specified otherwise in a construction contract or other binding agreement, within 30 days after receipt of a CO, the following close-out documents must be delivered by the Contractor to the Trust. 

3.2.1 Drawings, Calculations, Specifications, Revisions, Shop Drawings and Substitutions

The Contractor must provide three complete printed sets of as-built drawings, calculations and specifications, produced in a format approved in advance by the Trust. The sets must include any revisions, shop drawings and substitutions approved during construction (e.g., field changes and the final location of equipment and utility lines). 

 

In addition to the printed sets, as-built drawings must also be provided to the Trust in both PDF and AutoCAD format in the version then in use by the Trust. Calculations and specifications must also be provided in PDF format. CAD drawing files should be assembled to include all external reference files. CAD documents converted from file formats other than AutoCAD “DWG” files must follow guidance on formatting from Microstation. Electronic files must be delivered on a clearly labeled CD/DVD or on a USB memory stick. 

 

3.2.2 Keys, Special Tools and Spare Parts

Each article must be clearly labeled, noting the name and location of the building and/or site component with which the article is associated (door, appliance, heating or ventilation equipment, etc.). The Contractor must include any necessary instructions or other pertinent information. 

 

3.2.3 Material Safety Data Sheets

Material Safety Data Sheets must be provided according to standards established by OSHA. All sheets must be submitted in PDF format. 

 

3.2.4 Operating and Maintenance Manuals

Whenever a manufacturer produces an operating and maintenance manual for a fixture, finish, appliance or any other equipment installed by the Contractor, three complete printed sets of that manual, along with a PDF version, must be provided to the Trust. 

 

3.2.5 Post-Construction Contact Roster

Along with listing the Contractor, a post-construction roster must contain all project subcontractors, suppliers and manufacturers. The name, mailing address, e-mail address, telephone number (both landline and cellular) and facsimile number for each contact must be included in the post-construction roster. The roster must be submitted to the Trust in PDF format. 

 

3.2.6 Project Photographs

The Contractor must provide photographs documenting the project site, both interior and exterior, before and during construction and after project completion. All photos must be submitted in PDF format. A sufficient number of photos must be provided to clearly illustrate each trade and show work/installations per construction detail drawings. Each photo must be dated and labeled according to the Trust’s labeling convention, with location, including building number and compass coordinates. The following is an example of the Trust’s photo labeling convention, assuming a shot taken of the northwest view of Building 103 in August 2014: 2014.08.Building.103.NWview 

 

3.2.7 Warranties for all Installed Equipment, Fixtures and Finishes

Whenever a manufacturer produces a warranty for a fixture, finish, appliance, or any other equipment installed by the Contractor, that warranty must be provided in PDF format to the Trust. 

3.3 Project-Specific Documents

The approval or acceptance of any close-out document referenced in Section D.2.2 does not relieve the Contractor from additional requirements, depending on the project, its scope of work and binding terms and conditions. The TDR or other Trust representatives will provide assistance if additional close-out documents are necessary. Among the project-specific close-out documents that may be required are the following. 

3.3.1 Archival Submission

If documentation of historic fabric (building or landscape) is required for permitting, the Trust will also require an archival-quality copy of that documentation as part of the final project close-out. This may include, but is not limited to, measured record drawings and photographs. All submissions must comply with the requirements of the National Archives, records 49, 50 and 51. 

 

3.3.2 Disaster Plan

In general, disaster plans are developed to protect the safety of employees, visitors, contractors and others at risk from potential hazards. This includes incorporating procedures for persons with disabilities and functional needs. Disaster plans are also designed to prevent environmental contamination and protect facilities, physical assets and electronic information. 

 

3.3.3 Facilities Management and Safety Plan

A facility management and safety plan must describe the means and methods necessary to ensure that a site remains safe and well-maintained. It must include a list of scheduled inspections and repairs, waste and recycling protocols and a plan for safety training and emergency response, including incident, injury and accident reporting. 

 

3.3.4 Hazardous Material Inventory Statement

A hazardous material inventory statement must include details on the physical properties of each hazardous material stored or located at a site. These include the location of the material, its trade or chemical name, hazard class, quantity, container type and other information. 

 

3.3.5 Hazardous Material Management Plan

A hazardous material management plan must describe methods to ensure that each hazardous material at a site is stored and handled in a safe manner. It must also include a schedule of inspections and identify security measures, including how personnel will be trained for handling each hazardous material. The plan must also include detailed information for use by emergency responders. 

 

3.3.6 Historic Preservation Maintenance Plan

A historic preservation maintenance plan is generally comprised of a written inventory of historic building and site components that require periodic inspection and maintenance (e.g., building or site systems, fixtures and finishes). A preservation maintenance scope is required for each item. Additional information may be required, depending on the historic preservation scope. 

 

3.3.7 Investment Tax Credit Requirements

The Contractor is solely responsible for compliance with Section 106 of the National Historic Preservation Act, necessary to the tax credits review process. The process includes review by the California State Historic Preservation Office in Sacramento and the National Park Service Technical Preservation Services Office in Washington, D.C. Early coordination with Trust project and N2 staff in the preparation of a tax credit proposal is essential for successful completion of the tax credit review process. The Trust will work with the Contractor to resolve issues relating to the tax credit review process and may provide assistance during design and construction. Additionally, the Trust must review Parts 1, 2 and 3 of each tax credit submittal, along with all amendments, prior to their submission to the State Historic Preservation Office. A cover letter is also prepared by the Trust, either confirming concurrence with the submittal or describing specific concerns. 

 

3.3.8 LEED® Certification Documentation

A project of the U.S. Green Building Council, LEED® and its certifications focus on environmentally sound development and post-occupancy operating and maintenance practices. Documentation will depend on the type of project and certification category. 

 

3.3.9 Transportation Demand Management Plan

The goal of a transportation demand management plan is to help households, employees and visitors make more of their commute trips on transit, by bike or on foot, or in vehicles like taxis and car shares. Such a plan in the Presidio will incorporate transportation options offered by the Trust and other providers, including the PresidiGo shuttles.