See the requirements for construction in the Presidio.
2.1 Construction and Demolition Noise
2.2 Construction Trailer, Material and Waste Storage
2.5 Emergency and Other Contacts During Construction
2.6 Enforcement and Corrective Action
2.10.3 Special Inspections and Testing
2.12.2 Post-Occupancy Tenant Signage
2.14 Telephone, Data and Alarms
2.16 Procedures for Items Unearthed During Excavation
Following the pre-construction requirements outlined in Section 1, Section 2 addresses the requirements that apply to actual construction through the close-out of a project at the Presidio.
Construction equipment must be adequately muffled and maintained to minimize project noise (see Section 1.2.8). The Contractor and all equipment operators must comply with noise criteria established by the Trust, as well as with the standards and levels included in San Francisco Municipal Code Section 2909.27 Construction noise is limited to 80 dBA (A-weighted scale per American National Standards S-1.4-1971, or the latest approved revision thereof) as measured at the construction site boundary.
Job trailers, waste management containers and portable restrooms must be installed within the project site but outside of any right-of-way. Material storage and deliveries are also prohibited in a right-of-way.
The Trust requires recycling and documentation of construction debris that is diverted from landfills (see Section 1.1.1). All dumpsters and receptacles for food refuse must be water-tight, wildlife-proof and secured at all times. The Trust prohibits the accumulation of debris, litter or trash on construction sites.
Job sites require an on-site hazardous liquid material spill clean-up kit that contains a 25-pound bag of Floor-Dri (or its equivalent), absorbent pads and other materials for immediate clean-up. If hazardous liquids are stored at off-site laydown areas, this requirement applies there as well.
Tower cranes may be required at project sites with little or no setbacks. The Trust strongly prefers electric cranes because they generate less noise and no fumes or emissions. The Contractor must apply for a crane erection and setup permit and comply with OSHA regulations, including those associated with operator certification. The Contractor must maintain at the job site all records of crane inspection and certification (issued by a certifying agency or the OSHA crane certifier). Mobile cranes and concrete pumping rigs have the same requirements.
The Contractor is prohibited from trimming or pruning trees; if tree pruning is deemed necessary by the Trust, it will be undertaken by the Trust forestry crew.
Traffic control for project deliveries must be coordinated with the Trust’s Planning Department, with assistance from the TDR. Roads will not be closed unless the Trust grants an encroachment permit. The TDR may also identify possible staging locations for deliveries along approved haul routes.
Delivery and all other on-site vehicles are prohibited from idling for more than five consecutive minutes. The San Francisco Police Department enforces the San Francisco Municipal Transportation Agency’s traffic restrictions for local streets, including those leading to and from the Presidio gates.
If a construction-related emergency arises such as a sewer collapse or a water main break, the Contractor must immediately contact the Presidio Dispatch line at (415) 561-5656. Depending on the type of emergency, notification will be relayed to the Trust Utilities Department.
If a natural disaster or other type of emergency occurs, the Presidio Emergency Information Hotline, containing recorded information, will be activated at (415) 561-5656 or 911.
Other important contact information is as follows:
— MAIN OFFICE
1750 Lincoln Boulevard
San Francisco, CA 94129
(415) 561-5300
TTY: (415) 561-5301
www.presidio.gov
— WORK ORDER SERVICE CENTER
(415) 561-4270
woservicecenter@presidiotrust.gov
USPP Headquarters
1217 Ralston Avenue
(Fort Scott area)
(415) 561-5505 (non-emergency phone number)
The TDR is responsible for monitoring construction and will conduct random site visits to determine if operations are in compliance with the project’s approved CMP and other conditions and requirements, including protection of public safety. If a project is out of compliance, the Trust will impose corrective action in a three-step manner. The first step is a verbal warning and an explanation of the violation with a time-frame given for compliance. The second step is a written warning or correction notice with a time-frame given for compliance. The third and final step is a “Stop-Work Order” (or “Red Tag”). A Stop-Work Order immediately halts all activities until the violation(s) is corrected and the Contractor has demonstrated to the Trust’s satisfaction that there will be no recurrence of the violation(s).
Failure to correct any violation may subject the Contractor to fines or other penalties.
A temporary (i.e., removable) construction and site security fence approved by the Trust must be securely installed around the perimeter of each project site, as identified in the project’s SLP (see Section 1.1.6). At a minimum, the fence and gate(s) must be six feet in height and constructed of chain-link mesh with colored slats, the color of which must be approved by the Trust. Additional or alternative protection measures may be required by the Trust, depending on potential hazards or adjacent uses. Fence and gate post installations are subject to an excavation clearance.
All gates must accommodate emergency vehicle access and entrances must be kept clear at all times. All gates must be double-padlocked; one padlock will be provided by the Trust.
All haul routes are subject to Trust approval. All roadways in the Presidio are open for public use, including those that may be approved for construction hauling. The Contractor is encouraged to develop haul routes that maximize the use of the Presidio’s primary roadways, limiting disruption in residential areas and other sensitive locations. The Contractor must minimize the potential for conflict associated with the shared use of public roadways and limit delivery and construction vehicles to those capable of negotiating travel lanes in a safe manner. No construction traffic will be permitted on any roadways other than those approved for project hauling. Unless approved by the Trust, roads are not to be used to stage construction equipment or delivery trucks.
The Contractor is responsible for informing all subcontractors, vendors and suppliers of a project’s approved haul route. The Contractor must comply with the same weight restrictions that apply to San Francisco streets outside the Presidio gates. Over-sized vehicles and over-weight equipment transport require special encroachment permits and are subject to review and approval by the Trust.
The Trust reserves the right to change a designated haul route if conditions warrant.
Allowed hours of operation, including staging and deliveries, are limited to 7:00 AM to 6:00 PM, Monday through Friday. Work in residential areas may not begin until 8:00 AM. No construction is permitted on Saturdays, Sundays, or federal holidays. After-hours equipment maintenance at a project site is prohibited. Further restrictions may apply, including those referenced in Section 1.2.8 and those included in a project’s development agreement, lease, construction contract, permit, or other binding document.
Change to a work schedule, including staging of construction equipment and/or delivery of materials, requires written approval from the TDR at least 48 hours before the date of the proposed change. A request for work outside of the allowed hours of operation must include the reason for the proposed schedule change; number of workers and supervisors who will be on the site; location of the work (interior, exterior, etc.); equipment that will be used; and expected noise level or other impacts. Requests must include contact information for supervisory personnel.
The Presidio accommodates numerous activities and special events each year, especially on weekends, so the Contractor is encouraged to consult the current Presidio Special Events Schedule with Expected Impacts. The TDR may provide further guidance on schedule restrictions. The Trust reserves the right to place restrictions or additional requirements on activities scheduled outside of the allowed hours of operation.
During construction, the Contractor is required to facilitate any needed inspections and comply with the findings contained in the inspection reports. To minimize costs and maximize efficiencies, the Trust recommends the coordination of inspections and testing to reduce the number of site visits. The Contractor should consult with the permitting manager on specific requirements. Inspection request forms are available from the Permitting Office.
The Permitting Office will provide the Contractor with both a building permit job card and information on building inspection procedures.
An inspection will be scheduled to occur within 48 hours after the Permitting Office has received a completed request form for work that is ready for inspection. After the inspection is complete, the inspector will communicate either approval to proceed or the need to address outstanding issues, in which case a subsequent inspection will be required. A copy of all inspection request forms must be kept at the project’s job site office.
Elevator construction is governed by Chapter 30 of the IBC, supported by the American Society of Mechanical Engineers Safety Code A17, Safety Code for Elevators and Escalators. All elevator inspections are arranged by the Contractor and conducted by a Certified Competent Conveyance Inspector, certified by the State of California to inspect and certify elevators and lift systems.
Contractors must use an independent testing agency for code-required special inspections and tests. The special inspector observes work for conformance with approved construction documents and reports any non-conforming work. The special inspector makes regular reports, as frequently as daily, depending on the type of work to be inspected, and provides a final signed and stamped report (affidavit), filed with the Permitting Office. For assistance, the Permitting Office can provide a QVL of special testing and inspection firms. Contractors may not use a special testing or inspection firm that is not on that QVL without prior written approval from the Trust.
The Trust’s Special Inspection and Testing Schedule and Application is also available from the Permitting Office. Two copies must be completed and signed by the Applicant, the Engineer or Architect of Record, the Contractor and the special inspector. A pre-construction conference with the building inspector, special inspector, Contractor and applicable subcontractors may be required by the Permitting Manager to review the duties and responsibilities of the special inspector, inspection and testing procedures and schedule requirements. Communication to the special inspector for inspection appointments is the responsibility of the Contractor.
The Contractor is responsible for managing all lay-down and staging areas, including access, egress and on-site activities. BMPs must be applied at all laydown and staging areas. The use of lay-down and staging areas is subject to the same hours of operation and noise, dust and other restrictions imposed on the construction site, including those contained in the project’s SWPPP (see Section 1.2.11). The Contractor must provide security to the lay-down and staging areas and keep the areas free of trash and debris. If the Trust determines that fencing of a lay-down or staging area is necessary, the Contractor must provide, install and maintain the fencing material until project completion, at which time it must promptly be removed by the Contractor. Temporary resurfacing of a laydown or staging area, if required by the Trust, is also the responsibility of the Contractor.
Although the Trust reserves the right to deny a Contractor’s request for staging and lay-down space beyond the assigned construction site, if necessary, space outside of the construction area may be available for that purpose. At project completion, all lay-down and staging areas must promptly be returned to their pre-construction condition.
At least one construction sign must be posted at the project site that includes the project name and lists the Trust as property owner. The sign must not be an advertisement for the parties involved with the project and must only include the project’s basic information, such as building number, street name, primary project participants and the Trust’s emergency telephone number ((415) 561- 5656). The construction sign must be legible from the street. Details on sign material, mounting, fabrication and permitting are described in the Presidio Project Identification (Construction) Sign Signage Specifications. Construction signage requires approval and permitting from the Trust. Construction signage may be posted ten days before the start of construction and must be removed no more than ten days after project completion.
The Trust may also provide and mount interpretative signage, requiring coordination between the TDR and the Contractor. Construction and other project-related signage must be described in the project’s SLP (see Section 1.1.6). Limited directional signage at the Presidio gates may be provided by the Trust if necessary. No other signs are permitted.
Exterior tenant signage may be installed during the course of construction or after occupancy commences. All such signage must conform to the Presidio Sign Standards & Guidelines.
Staging of construction equipment or delivery vehicles within the Presidio is discouraged. Prior review and approval from the Trust’s Planning Department is necessary for special operations, including staging of concrete “readi-mix” trucks, material delivery transports, heavy equipment set-up, or any activity that might require a temporary road closure(s). The Trust may limit staging locations, number of trucks and duration of operations.
Right-of-way encroachments are used only as a last resort. If a right-of-way encroachment is necessary, the TDR will assist the Contractor in processing an application for an encroachment permit through the Trust’s Planning Department. The Trust’s Marketing & Communications Department must be notified of any impending encroachment and will determine what type of further notification, if any, will be required (see Section 1.4). An encroachment permit application requires an operation-specific TCP that is designed by a state-certified traffic control supervisor or civil engineer (see Section 1.2.12). A minimum of two business days is needed for processing an encroachment request.
The TDR will assist the Contractor in planning for new telephone and data service that conforms to Trust requirements. The Contractor is responsible for distribution of telephone and data lines and for contacting and making arrangements with a selected telephone carrier and internet service provider.
Fire, life-safety and security alarm systems require analog lines. To monitor mandatory fire life-safety systems, the Trust will provide two analog numbers to each commercial building. Tenants must order a separate analog circuit from a telephone carrier for security alarm system monitoring. An in-cab telephone line is required in building elevators for emergency notification.
The Trust’s Utilities Department is responsible for providing the following services to all buildings in the Presidio:
A completed utility application is required to initiate utility service planning, assignment of accounts, or temporary or permanent service. Utility applications and service rate sheets are available from the Trust’s Municipal Services Department.
The Trust’s Utilities Department purchases electrical power from PG&E and distributes it through the Trust’s high-voltage system. PG&E also owns and operates the distribution network through which natural gas is supplied to the Presidio. If a viable gas meter is present, it is the responsibility of the Applicant or Contractor to contact PG&E to open an account to receive gas service. If no functional gas meter exists, the Applicant or Tenant must contact the Trust’s Infrastructure Management team to establish new gas service.
The Trust operates its own water treatment facility in the Presidio and distributes water from a reservoir in the Presidio through a Trust-owned distribution system. While the Presidio’s own sources provide most of the water in the park, the Trust purchases supplemental water from the San Francisco Water Department when needed. The Trust also provides the collection system for waste water, which is conveyed via connector lines to San Francisco’s Department of Public Works’ system for treatment.
The Trust’s Utilities Department operates and maintains a separate system for the collection and disposal of storm water. This system is comprised of storm sewer pipes, open channels and retention ponds all acting together to convey storm water away from structures and inhabited areas for discharge into Crissy Field and the San Francisco Bay. It is a federal offense to dispose of anything other than water runoff into the Presidio’s storm drain system.
All domestic and fire service lines installed by the Contractor must be inspected, tested, chlorinated and flushed, with oversight required by the Trust’s Water Department. Upon satisfactory water sample test results, the Contractor must coordinate with the Trust’s Water Department to tap the water main, make final connections and install water meter(s). Unless otherwise stipulated by written agreement, all costs associated with inspecting, testing and connecting to water lines are borne by the Contractor. The Presidio’s water system connection procedure and associated requirements are defined in the Trust’s Water Distribution Specification.
Utility service interruptions may be needed for a variety of reasons during a construction project. To ensure timely notification to the Trust’s customers, the Contractor must request a service interruption at least 15 business days before the anticipated event. Interruption requests are made using the Trust’s Planned Shutdown Input Sheet. Notifications to residents and commercial tenants about planned outages are coordinated by the Trust’s Utilities Department.
The Trust provides temporary construction-related water and electrical service. The Contractor is responsible for providing temporary electrical panels and distribution. Backflow preventers are required for all temporary water service hook-ups.
The Contractor must submit an application to the Trust’s Municipal Services Department for temporary utility service through the TDR, including anticipated capacity loads, project site stub-out locations and service dates. Once the application is approved, the Trust’s Utilities Department will identify special requirements, if any, and establish a billing account.
Even when a site is outside of a known zone of interest and is not considered an area of archaeological significance, unusual artifacts and military objects, including unexploded ordnance (“UXO”), may still be found. Should excavations disclose or unearth an object of potential historical, military, or archaeological interest or significance, the Contractor must immediately stop work, leave the object in place and note its position. The Contractor must also immediately notify the TDR and allow Trust specialists to determine the next appropriate response, including the appropriate disposition of the disclosed or unearthed item(s) and the terms under which excavation work may be resumed. Failure to follow these procedures is a violation of federal law.