See the requirements for pre-construction in the Presidio.
1.1 Construction Management Plan (“CMP”) – Required for All Projects
1.1.1 Construction Debris Recycling Plan
1.1.2 Exhaust Measures for Construction Equipment and Vehicles
1.1.3 Construction Sequence and Project Schedule
1.1.4 Construction Parking and Traffic Management Plan (“CPTMP”)
1.1.6 Site Logistics Plan (“SLP”)
1.1.7 Site-Specific Safety and Health Plan (“SSHP”)
1.2 Project-Specific Submittals
1.2.1 Cultural Resources Protection Plan (“CRPP”)
1.2.2 Demolition and Material Salvage Plan
1.2.3 Dust Prevention and Control Plan (“DPCP”)
1.2.4 Excavation, Shoring and De-Watering Plan
1.2.5 Hazardous Material Abatement Plan (“HMAP”)
1.2.7 Natural Resources Protection Plan (“NRPP”)
1.2.8 Noise Suppression Plan (“NSP”)
1.2.9 School Traffic Control Plan
1.2.10 Site-Specific Soil Management Plan (“SSSMP”)
1.2.11 Storm Water Pollution Prevention Plan (“SWPPP”)
1.2.12 Traffic Control Plan (“TCP”)
1.3.1 Pre-Construction Conference
1.3.2 District Construction Coordination Meeting
1.4 Notifications to the Public, Presidio, Residents and Tenants
The Contractor is required to submit a CMP to the TDR. An approved CMP is also required for projects undertaken directly by the Trust. A CMP describes how construction will be planned and administered and is tailored to the project’s specific scale and level of complexity. While the TDR may advise the Contractor on the CMP’s content, the Contractor is responsible for development and implementation of the CMP. The CMP must be approved by the Trust before construction can commence. A copy of the approved CMP and any approved amendments must remain at the job site until a Certificate of Occupancy is issued by the Trust.
While the following documents are required for every CMP, additional documents may be necessary, depending on a project’s scope and expected impacts (see Section 1.2).
Because the Trust records all construction waste management activities in the Presidio, each Contractor must prepare a CDRP, describing how construction debris will be documented, collected, sorted and quantified. Construction projects are required to divert 100% of all Portland cement concrete and asphaltic concrete from landfills and to divert at least 65% of all remaining construction and/or demolition debris. If construction debris is to be mixed and transported to an off-site facility for processing, the CDRP must identify the registered transporter and the registered facility. Quantities are based on weight unless volume is more appropriate.
For further information, refer to the Trust’s Format for Contractor’s Solid Waste Management Plan and Waste Minimization Checklist for Deconstruction and Demolition. The TDR will provide additional direction if a project is to be LEED® certified and the classifications of construction debris or salvaged building materials used by LEED® are different from those used by the Trust.
The Contractor must develop an idling policy that complies with the PTMP’s Environmental Impact Statement condition for construction equipment emissions. Additionally, the Contractor must document that all construction equipment and vehicles conform to applicable requirements, which can be found on the California Air Resources Board website. These requirements include, but are not limited to, the following:
The Trust requires project sequencing information and an overall schedule for every project in the Presidio. The project schedule must be developed with Microsoft Project (version 2010). The Contractor is responsible for obtaining the schedule template (format and calendar) from the TDR and for creating and updating the project schedule. Unless otherwise directed, the project schedule must be updated monthly during construction and submitted to the TDR for review and approval. The schedule must be detailed and show individual tasks, anticipated start and finish dates, critical paths and milestones, resources and work progress summaries. A narrative is also required that fully describes the general construction approach, its work phases and sequencing.
The Trust regulates all parking and traffic in Area B of the Presidio, including that associated with construction. The United States Park Police (“USPP”) has sole authority to issue citations.
The CPTMP must include measures to ensure consistent compliance with existing regulations throughout the course of construction, including limitations on haul routes. The CPTMP must also contain information on how its contents will be communicated to the Contractor’s personnel, subcontractors, suppliers, vendors and others. For specific information on haul route restrictions, see Section 2.8.
The Contractor is responsible for each designated construction parking area, including security, access and egress, and trash and debris removal. If the Trust determines that fencing of a construction parking area is necessary, the Contractor must provide, install and maintain the required material. Contractor must remove the required fencing as soon as the construction parking area is no longer in use. Construction-related parking is unlikely to be available at no cost, unless specifically provided for through a construction contract or other binding project-related document. Parking in residential neighborhoods is generally restricted to residents with permits. Depending on the project, its location and impacts, temporary parking permits for construction-related vehicles in a residential area may be available through the TDR. Designated construction parking areas may not be used for lay-down of construction materials. The Trust encourages the use of public transportation and other alternatives to single-occupant vehicles. To facilitate this, the Trust operates Presidio Go, a free shuttle service with routes both around the park and to downtown San Francisco. The downtown shuttle links the transit center in the Main Post to the financial district, with stops at the intersection of Union Street and Van Ness Avenue, the Embarcadero BART station and the Transbay Terminal. The TDR can help make arrangements for Presidio Go passes. The TDR can also provide information on transportation options such as carpooling, vanpooling, or the use of private shuttles for transporting workers to project sites or to off-site parking areas. If third-party shuttle service is proposed, the Contractor must submit details of the proposed service to the Trust for review and approval. Use of vehicles and drivers for organized transport of passengers within the Presidio is subject to applicable provisions of California law.
A project roster must be developed and distributed to all project personnel. The roster must include the name, mailing address, e-mail address, telephone numbers (both landline and cellular) and facsimile number for the following project contacts:
The SLP must show the entire project site on one plan sheet. Additional plan sheets must include a project vicinity map that depicts the general project site location within the Presidio; delineates project site boundaries, including building footprint(s); and identifies neighboring buildings and adjacent streets. A legend must indicate the scale of the drawing and provide an arrow showing north directed toward the top of the plan sheet.
The SLP must describe the job site set-up and depict locations for the following items, as applicable:
The SLP must also include anticipated start dates (including initial mobilization) and finish dates for each phase or stage of work. A new plan sheet must be created each time a modification is made.
The Contractor must submit a SSHP for review and approval by the Trust that covers all on-site work to be performed by the Contractor and all subcontractors. All work performed in the Presidio is governed by the Federal Occupational Safety and Health Administration (“OSHA”) and must comply with all applicable federal occupational health laws and regulations. This includes, but is not limited to OSHA Standards 29 CFR Part 1910 and Part 1926. OSHA representatives may perform periodic job site safety inspections.
The Contractor is responsible for obtaining all necessary OSHA permits for specific construction operations, if applicable. The Contractor must also provide annual activation notifications for all project permits. The Contractor must specifically note in the SSHP when a more stringent criterion or standard is being applied (e.g., California OSHA). Environmental and safety awareness training will be required for all construction workers. Other minimum requirements are explained in the Trust’s Outline for Site-Specific Health and Safety Plan.
As work progresses, the SSHP must be adapted to any unanticipated job situations or conditions.
The approval or acceptance of any document, or issuance of any permit referenced in Section 1.1, does not relieve the Contractor from additional requirements, depending on the project’s scope of work. The TDR or other Trust representatives will provide assistance if additional measures are required. Each additional project-specific submittal will need Trust review and approval before construction can commence. Among the project-specific submittals that may be required are the following.
Cultural resourcesi, including cultural landscapesii, that may be affected by project activities must be identified early in the pre-construction process. Depending on the project’s scope of work, a Contractor may be required to submit a CRPP to the Trust for review and approval. All cultural resource protection measures identified in an approved CRPP must be in place before construction or demolition activities can begin. N2 staff are available to assist in the preparation of a CRPP.
A demolition and material salvage plan must be prepared and submitted to the Trust for review and approval if a project requires the demolition or salvage of architectural building elements. All salvaged building material will continue to be the property of the Trust, unless provided for otherwise in a development agreement, lease, construction contract, permit condition, or other document governing the project. If material is salvaged off-site, it is to be delivered to a location specified by the TDR. For additional guidance, the Contractor may request the Trust’s Waste Minimization Checklist for Deconstruction and Demolition.
A DPCP is required for all projects that will create dust emissions. The DPCP must either demonstrate that there will be no discharge of dust from the construction site or, if dust will be discharged, include documentation of how the Contractor will reduce construction-generated particulate matter emissions to a level acceptable to the Trust (PM-10 standard).iii For building demolition projects, the Contractor must file an application for a permit with the Bay Area Air Quality Management District (“BAAQMD”) at least ten working days before the commencement of work. Depending on the scope of the work, the same may be true for rehabilitation or other types of projects in the Presidio.
i Definition of cultural resource: An aspect of a cultural system that is valued by or significantly representative of a culture or that contains significant information about a culture. A cultural resource may be a tangible entity or a cultural practice. Tangible entities at the Presidio include archaeological resources, cultural landscapes and historic structures.
ii Definition of cultural landscape: The organization and inter-relationships of the natural and designed features of a site by use reflecting cultural values and tradition and changes to those features over time. At the Presidio, this character is inextricably linked to its military occupation from 1776 to 1994.
iii The PM-10 standard includes particles with a diameter of 10 micrometers or less (0.0004 inch or one-seventh the width of a human hair). The U.S. Environmental Protection Agency’s health-based national air quality standard for PM-10 is 50 micrograms per cubic meter (“μg/m3”) (measured as an annual mean) and 150 μg/m3 (measured as a daily concentration).
Depending on the scale of the project, a water truck may be required for dust control. In such cases, the TDR or Trust construction manager will review the scope of earthwork activities to determine the appropriate amount of watering. Under dry conditions, a site may require watering three or more times per day. Trucks hauling soil, sand or any other loose material must be covered. Vehicle speeds on construction access roads and within any construction site may not exceed posted limits or 15 miles per hour, whichever is lower.
The DPCP must include the name, mailing address, telephone numbers (both landline and cellular) and facsimile number of the person who will be available to the project on a 24-hour basis throughout the course of construction. The same information must be included in the project roster (see Section 1.1.5). The DPCP must include a description of site conditions during construction operations, including outside of normal working hours and during each specific phase of construction. It must also detail how dust creation and transmission with be reduced or eliminated, including, but not limited to the following:
Excavation and shoring plans are considered during the Trust’s building permit review and general permit conditions are issued by the Trust. The Contractor and relevant subcontractors may need to obtain or activate additional permits from OSHA for trench work, if required by specific site conditions.
If de-watering is required, a de-watering plan must be submitted to the Trust’s Water Department for review and approval. The plan must describe how any groundwater will be pumped, stored, tested and ultimately discharged. An additional discharge permit may be required from the Trust Water Department if groundwater is to be discharged into a storm water or sanitary sewer system.
If de-watering is required, it must also be identified in a Storm Water Pollution Prevention Plan (see Section 1.2.11).
Asbestos-containing material (“ACM”) and lead-based paint (“LBP”) are present in many Presidio structures. Activities such as demolition, repair or rehabilitation may disturb ACM, LBP or other hazardous materials.
If a project requires hazardous material abatement of any type, a HMAP must be prepared and submitted to the Trust for review and approval before abatement can occur.
The Contractor must address the investigation, disturbance, handling, disposal and/or remediation of both ACM and LBP in accordance with Trust specifications and all applicable local, state and federal laws, codes, regulations and standards governing the work. These include, but are not limited to, those from the U.S. Department Housing and Urban Development, the U.S. Environmental Protection Agency (“EPA”), BAAQMD, OSHA, the National Institute for Occupational Safety and Health, the California Occupational Safety and Health Administration and the California Department of Public Health. Whenever there is a conflict or overlap among the above-referenced laws, codes, regulations, or standards, the more stringent applies.
All workers performing regulated work must be appropriately trained and, depending on the activity, certified. Disposal is addressed in the Trust’s Disposal Requirements for Asbestos-Containing Material and Lead. The Trust reserves the right to disturb soil and/or plantings adjacent to any building at any time in order to investigate or remediate possible hazardous material.
The National Park Service Archive and Record Center has reports contracted for by the U.S. Army that document the presence of specific locations of ACM at Presidio buildings. The TDR can help arrange a review of these documents.
In most cases, the Trust will require the Applicant to produce documentation of any historic landscape, building or building fabric to be altered or demolished. Documentation must be produced and approved by the Trust before the alteration or demolition can occur. Methods may include measured record drawings, photo documentation, or, possibly, curation of salvaged materials. The Trust will require an archival-quality copy of the Applicant’s applicable historic documentation as part of the final project close-out submittal (see Section 3.3.1).
Measured base drawings and site surveys are necessary to develop rehabilitation plans at the Presidio. While there are plans for most buildings in the National Park Service Archive and Record Center, their accuracy is rarely sufficient to develop accurate construction drawings. N2 staff are available to assist in the collection of historic documentation in preparation for project reviews.
All construction projects in the Presidio are required to adopt measures to protect natural resources from the impacts of construction activities. Unless determined otherwise during the Trust’s pre-construction design and compliance review process, the Contractor must submit a NRPP for Trust review and approval. All natural resource protection measures identified in an approved NRPP must be in place before construction or demolition activities can begin.
The Contractor must provide for tree protection, including compliance with specific actions that may be required by the Trust’s forester. In addition to the Trust’s Standard Tree Protection Measures, the Contractor may refer to the VMP for information on vegetation and tree protection, trimming and removal.
The Trust’s Wildlife Implementation and Monitoring Plan provides guidance on vegetation protection. Trust natural resource specialists will assist in selecting appropriate measures to protect nesting birds and other wildlife.
An NSP is required if construction noise measured at the construction site boundary is expected to exceed 80 decibels (“dBA”) (A-weighted scale per American National Standards S-1.4-1971, or the latest approved revision thereof as measured at the construction site boundary). Construction noise is limited to 80 dBA (A-weighted scale per American National Standards S-1.4-1971, or the latest approved revision thereof) as measured at the construction site boundary. Activities that generate noise in excess of 80 dBA are restricted to the hours of 9:00 AM to 5:00 PM, Monday through Friday. An NSP shall be based on specific anticipated equipment and construction methods.
A school traffic control plan must be submitted for most projects located near a school, as determined by the Trust. If the project is not located near a school but abuts a school bus stop or school walk route, extra traffic control personnel and devices are required to ensure school bus and pedestrian safety during school hours. The TDR can provide a map of existing schools in the Presidio.
An SSSMP details how soil at the project site will be managed and must comply with the requirements and procedures outlined in the Trust’s Presidio Soil Management Guidelines.23 The SSSMP must describe soil-disturbing activities, including excavation and grading of site soils, import of fill soils and disposal of excess soil. The Presidio Soil Management Guidelines, which are managed by the Trust Remediation Department, describe procedures for characterizing soils, requirements for soil re-use at the project or elsewhere in Presidio and requirements for off-site disposal. The Trust Remediation Department will review the SSSMP. The SSSMP must be approved before the work can begin.
Construction projects that disturb less than one acre of soil must adhere to the Trust’s Storm Water Management Plan. Using criteria of the California Water Resources Control Board, dischargers whose projects disturb one or more acres of soil are required to obtain coverage under the General Permit for Discharges of Storm Water Associated with Construction Activity. Construction activities subject to this permit include clearing, grading and disturbances to the ground such as stockpiling or excavation. The Construction General Permit requires the development and implementation of a SWPPP. The SWPPP must contain a site map(s) that shows the construction site perimeter; existing and proposed buildings, lots, roadways and storm water collection and discharge points; general topography both before and after construction; and drainage patterns across the project. The SWPPP must list best management practices (“BMPs”) that the discharger will use to protect from storm water runoff and the placement of those BMPs. Additionally, the SWPPP must contain monitoring protocols. Section A of the Construction General Permit describes the elements that must be contained in a SWPPP. The California Stormwater Quality Association’s Construction Best Practices Handbooks are available for additional reference.
A SWPPP must be written by a SWPPP developer certified by the California Water Resources Control Board. The certified SWPPP developer must provide the TDR with all permit registration documents for review and approval before submitting to the California Water Resources Control Board.
Once approved by the Trust, the permit registration documents will be electronically filed by the Trust’s assigned signatory with the California Water Resources Control Board’s Storm Water Multiple Application and Report Tracking System (“SMARTS”). The assigned signatory will provide data entry rights to SMARTS so the Contractor can manage (and amend, if required) the SWPPP throughout the duration of the project. Copies of the SWPPP will be provided to the Trust’s assigned signatory and the project’s TDR. A copy of the SWPPP must be kept at the construction site for review at all times.
At the conclusion of the project, a site walk with the TDR will be required to ensure that all work is complete, the site is in stable condition and final erosion control measures, if any, have been properly installed. Any outstanding conditions identified at the site walk must be remedied to the Trust’s satisfaction. A subsequent site walk will likely be required for this purpose.
Once the Trust determines that the site is in satisfactory condition, the TDR will direct the Contractor to complete a Notice of Termination, available on-line from SMARTS. Once complete, the Contractor will request that the Trust’s assigned signatory certify the Notice of Termination via SMARTS. Final approvals from SMARTS will be retained by the Trust.
Depending on a project’s scope, a TCP may be required by the Trust. A TCP must be developed by a state-certified traffic control supervisor or civil engineer and conform to the then-current edition of the California Manual on Uniform Traffic Control Devices. Among other requirements, a TCP must address the control of traffic entering and exiting a project site and describe how signage, safety zones and flaggers will be used. In addition to vehicular traffic, the TCP must also address pedestrian and bicycle traffic.
Contractors are required to attend the following conferences and meetings.
A pre-construction on site meeting is required for all projects before mobilization can occur. The purpose of the meeting is to review and confirm Presidio-wide requirements and project-specific protocols and conditions. The meeting is organized in coordination with the TDR and will include the Contractor’s key staff and Trust support staff, including the Federal Preservation Officer, utility personnel and other specialists, depending on the project’s scope of work. A separate pre-construction meeting focused on inspections and testing may be required by the Permitting Manager, also depending on the project’s scope of work.
Contractors working on projects in close proximity to each other or within the same Presidio planning district must attend weekly district meetings. The purpose of the meetings is to coordinate activities to minimize the potential for conflicts; improve efficiency and safety; and reduce impacts on the public, residential and commercial tenants and Trust operations. Each Contractor must provide a “3 week look-ahead” schedule at each meeting, along with supporting exhibits necessary for effective coordination (e.g., staging and hauling plans, locations of temporary road closures, anticipated utility outages, etc.). Each Contractor must have decision-making authority for their respective project. The Trust is the final decision-maker, should conflicts arise involving project coordination.
Advance notification is required for activities that may affect the use and enjoyment of the Presidio by the public and/or the Presidio’s non-residential and residential tenants.
The Contractor must work with their Project Manager or TDR to develop a public information plan for projects with significant public impacts, as determined by the Trust. The public information plan must be approved by the Project Manager or TDR before mobilization can begin. Public notification will be issued by the Marketing & Communications team at its discretion. Unless otherwise directed by the Trust, the Contractor must submit a monthly project update to the TDR that includes a description of the current project phase of work, a “look ahead” to activities occurring in the next reporting period, identification of any traffic and pedestrian concerns, a description of noise-generating activities and a description of hauling and staging operations. The Project Manager or TDR may use information from these reports at its discretion. If the project site has a “web cam,” arrangements can be made with the TDR to post images on the Trust’s website.
For projects with limited impacts or impacts that are generally expected to affect only non-residential and/or residential tenants of the Presidio, the TDR will submit draft notifications to the Trust’s Real Estate Asset Management Department for review and approval. Notifications must contain a general project description, construction schedule, hours and days of operation, summary of expected impacts (e.g., noise, temporary parking changes, anticipated power outages, etc.) and contact information for the project’s TDR. If applicable, haul routes, traffic detours and other transportation controls must also be included.
The notifications must be approved by the Trust’s Real Estate Asset Management Department at least 15 working days before mobilization is expected to occur.
Staff of the Real Estate Asset Management Department or the respective property manager will send the notifications to non-residential and residential tenants 5 to 10 working days before mobilization is expected to occur.
The USPP provides all police services in the Presidio. The San Francisco Fire Department provides fire and emergency services to the Presidio. All alarm systems are required to report to the Presidio’s central alarm monitoring facility.
As the designated Authority Having Jurisdiction in the Presidio, the FPO is responsible for the following activities:
All new construction and all existing buildings undergoing major rehabilitation, alteration, or change of use require fire sprinkler and fire alarm systems. The FPO requires separate permits for fire sprinkler and fire alarm installations. Each sprinkler and alarm system must be installed by a Trust-approved professional fire and life-safety contractor, licensed to design, install, certify, service, test and maintain the specific system. Upon request, the FPO can provide a QVL of fire and life-safety contractors.
Fire alarm, smoke detection and fire sprinkler systems must comply with Fire and Life Safety Codes as adopted by the Trust. The FPO can provide detailed requirements for alarm, smoke detection and fire sprinkler systems, including requirements for how these fully addressable systems must communicate with the monitoring facility.
The USPP Physical Security Specialist is responsible for reviewing and approving security systems prior to installation and will evaluate the Applicant’s intrusion alarm selection, access controls, security lighting and landscaping. The TDR will coordinate review to ensure compliance with N2 and other potential requirements.
The Physical Security Specialist will assist the Applicant with physical security considerations and risk assessment and also can provide a current copy of the USPP’s Guidelines for Physical Security Installations. Specific intrusion prevention measures (e.g., security cameras, alarms, etc.) are chosen by the Applicant.
Alarm-related contractors are subject to Presidio Trust approval. The USPP can provide a QVL of contractors to design, install, service, test and maintain alarm control systems in the Presidio.
All Trust facilities must be accessible to responding emergency crews 24 hours a day. The Trust requires that all non-residential facilities be equipped with a Knox Box, typically installed at the primary response entrance, as designated by the FPO. The method of mounting the Knox Box depends on the type of building and must be coordinated by the TDR and the FPO. The Contractor is responsible for purchasing and installing the Knox Box at the approved location.